Virginia Conservation Network Takes Position on NextEra-Dominion Energy Merger

Data center transmission line in Loudoun County. Photo by Hugh Kenny, PEC.

Virginia’s energy landscape is changing rapidly. As data centers drive unprecedented growth in electricity demand, decisions about who generates our power, how it is delivered, and who pays for new infrastructure will shape the Commonwealth for decades to come. The proposed $67 billion transaction would create the world’s largest regulated electric utility. NextEra Energy has identified expanding its role in serving large energy users, including data centers and artificial intelligence (AI) facilities, as a central reason for pursuing the deal.

For Virginia, this raises important questions about whether the combined company will prioritize the needs of communities and customers or prioritize the acceleration of data centers that rely on more infrastructure, higher electricity demand, and continued investment in fossil fuels.

That’s why Virginia Conservation Network (VCN) is opposing NextEra Energy’s proposed acquisition of Dominion Energy.

Threats to Virginia’s Clean Energy Future

The Virginia Clean Economy Act (VCEA) requires regulated electric utilities to retire carbon-emitting electricity generation by 2045. However, NextEra Energy stated in its 2025 Environmental Stewardship Report that it no longer sees “a realistic path to achieving actual zero-carbon emissions by 2045.” The company has also continued investing in fossil fuel infrastructure, including increasing its ownership stake in the Mountain Valley Pipeline.

Expanding fossil fuel infrastructure in Virginia could undermine the Commonwealth’s clean energy transition while creating additional pollution and impacts to our air, water, wildlife, and natural lands.

Higher Costs for Virginia’s Households

The merger also raises concerns about long-term electricity affordability. NextEra Energy’s experience operating Florida Power & Light offers a concerning case study: between 2021 and 2025, the average FPL customer experienced an increase of more than 30% in monthly electricity bills. In 2024, FPL disconnected nearly 1.3 million households that could not afford their bills.

The companies have proposed approximately $1.78 billion in bill credits for Virginia customers, potentially providing the average household with about $10 per month for four years. While these credits offer temporary relief, they do not address the long-term costs of building new generation, transmission, and data center infrastructure. Virginia customers deserve lasting affordability protections, not just short-term bill credits.

Greater Utility Influence

NextEra Energy and its affiliates have also spent more than $60.8 million on state-level campaign contributions in Florida between 2010 and 2025, raising concerns about the relationship between utility companies and the agencies responsible for regulating them. In Virginia, where corporate political spending faces relatively few restrictions, the merger could give the combined company significantly greater influence over state energy policy and regulatory decisions.

Virginia’s Energy Future Must Put People and the Environment First

VCN recognizes the complexity and magnitude of this proposed transaction, but the potential consequences warrant serious consideration. Virginia needs an energy utility company that prioritizes affordable and reliable electricity, protects our natural resources, advances our clean energy commitments, and holds utility companies accountable to the communities they serve.

VCN opposes the proposed NextEra-Dominion Energy merger because of the risks it poses to our environment, electricity customers, and democratic processes. As state and federal regulators review the acquisition, they must prioritize the long-term public interest and ensure Virginia’s energy future is not dictated by the business interests of an increasingly consolidated utility industry.