RESPONSIBLE DATA CENTER DEVELOPMENT

Nate Benforado // Southern Environmental Law Center // nbenforado@selcva.org

Julie Bolthouse // Piedmont Environmental Council // jbolthouse@pecva.org

Kyle Hart // National Parks Conservation Association // khart@npca.org

Victoria Higgins // Chesapeake Climate Action Network // vhiggins@chesapeakeclimate.org

PDF Download

Land Use & Transportation

Why It Matters

Virginia is home to the largest concentration of data centers in the world, with a combined power consumption capacity about four times greater than the next closest American markets, Dallas and Silicon Valley1. This massive industry is continuing to grow rapidly, requiring huge amounts of energy, land, and water to operate, resulting in widespread community impacts.

One data center can use as much energy as thousands of households; in fact, a large “hyperscale” data center can consume over 100 MW of power2, which equates to the power consumed by approximately 80,000 households. As of early 2023, data centers make up 21% of Dominion Energy’s power load in Virginia3, with PJM’s projections indicating a doubling of the state’s peak electricity demand through 20384.

While Dominion has a long history of predicting more growth than occurs, electricity consumption has increased significantly over the past four years5 and their high projections6 and “electric service agreements”7 with the data center industry are being used to justify dozens of new substations and expensive transmission projects to serve data center load requests throughout the state8,9 as well as new polluting gas facilities that would increase all ratepayers’ electric bills significantly despite the need being driven almost entirely by data centers.

Data centers can also have significant local air quality impacts. Data centers around Virginia rely on diesel generators as a backup electricity source. In Northern Virginia, data centers have obtained air permits for over 4,000 diesel generators with a combined capacity of over 11GW of power10,11 –more than all of Dominion’s entire gas generator fleet. There is no monitoring of the impacts on air quality from periodic testing of these generators which is usually done monthly12 or any analysis on the impact if there were a transmission level outage.

Data center campuses are getting larger, requiring massive amounts of land and water. Projects over 1,000 acres have been proposed directly adjacent to national and state parks, threatening the integrity of Virginia’s landscapes and wildlife corridors. Despite prioritizing reclaimed water for data center cooling in the past, Loudoun County’s data center potable water consumption is now higher, having increased by 250% in the last 4 years, totaling 899 million gallons in 202313. Data center development expectations in other parts of the state are also triggering additional surface water withdrawal requests14.

The nexus of land, energy, water, and ratepayer impacts represents a complex challenge–and immense opportunity–to protect Virginia’s environmental resources.

Current Landscape

For years, statewide tax incentives and active recruitment by both state and local economic development offices have encouraged data centers to continue siting in Northern Virginia, despite its existing heavy concentration of data15. Coupled with skyrocketing demand following the 2020 pandemic, Northern Virginia as well as other markets throughout the state are experiencing exponential growth. Unfortunately, there has been no proactive planning or adjustment to the state tax incentives to address this shift and the need to protect the resources of the state. Without sufficient regional or statewide oversight, localities continue to approve more facilities without considering the statewide and nationwide impacts on the electric grid, ratepayers, water supply, national and state parks, or air pollution.

The concentrated data center growth in Northern Virginia has also resulted in a congested grid that is already in need of significant transmission projects. PJM, for example, recently approved a $5B portfolio of transmission projects that would expand grid connections from West Virginia, Pennsylvania, and Maryland to the Northern Virginia data center market. One of the major projects in that portfolio is the Mid-Atlantic Resiliency Link traversing from data center alley out to West Virginia where the power generation is primarily coal and gas-fired power plants16.

In December 2023, the Joint Legislative Audit & Review Commission (JLARC) passed a resolution17 to study data centers and better understand these wide-ranging impacts. That study remains ongoing, and it should help guide decision-makers. However, the energy costs18,19 and many of the environmental impacts of data centers are already well known.

Opportunities

It is time for the state to play a larger role in planning for and mitigating the impacts of this explosive industry. As one of the largest industries in the state, data centers require greater transparency and oversight to ensure that their development is happening in a sustainable manner that benefits communities without harming our health and natural resources.

The current review process is inadequate at both the local and state level. Localities, for example, are making decisions about large data center projects with little to no information about the significant ramifications on the state’s electric grid and ratepayers, water supplies, air quality, or carbon emissions. During the local approval process, localities should be required to consider information about the potential grid impacts of a data center proposal, including energy demand, required infrastructure, and interconnection conditions. For particularly large data center projects, this review could happen at the state level to help ensure continued grid reliability and prevent excessively high costs from falling to the ratepayers. In addition, a state-level review could evaluate impacts on shared regional resources or state goals not usually in the localities’ purview to address, such as the protection of national and state parks, water supply, and air quality.

In addition, as grid infrastructure costs add up, Virginia needs to be sure that the SCC and other agencies have the appropriate tools to ensure that data center companies are paying their fair share of transmission, distribution, and generation costs.

A final important opportunity is to revisit the state’s tax incentives. The current approach continues to attract development but has failed to incentivize data center companies to mitigate environmental and community impacts. A revamped tax incentive could encourage clean energy commitments, energy efficiency standards, innovative demand shifting and peak shaving that reduce facility’s energy consumption, diesel generators phase-out, efficient cooling water systems, and buffers from parks, homes, schools, and nearby communities.

Top Takeaways

Local review of data center developments is inadequate to evaluate widespread impacts on the grid, electric ratepayers, water resources, parks, air quality, and emissions, and a state review process is necessary.

With data centers representing the driving force behind significant load growth projections, it is important to ensure the industry is paying its fair share and costs aren’t falling on all utility ratepayers.

Virginia already has the largest data center market in the world, so state incentives should be tightened to encourage data center proposals that are more sustainable.

End Notes

1 Peasley, Julie, “Ranked: Top 50 Data Center Markets by Power Consumption,” Visual Capitalist, (June 28, 2024).https://www.visualcapitalist.com/cp/top-data-center-markets/.

2 Powell, Phill and Ian Smalley, “What is a Hyperscale Data Center?” IBM. (June 28, 2024). https://www.ibm.com/topics/hyperscale-data-center.

3 Dominion Energy. “Quarterly Report Q4 2022,” (June 26, 2024). https://investors.dominionenergy.com/financials-and-reports/quarterly-materials/default.aspx.

4 “PJM Load Forecast Report,” PJM Resource Adequacy Planning Department, (January 2023). https://www.pjm.com/-/media/library/reports-notices/load-forecast/2023-load-report.ashx.

5 “Commercial electricity demand grew fastest in states with rapid computing facility growth,” U.S. Energy Information Administration, (June 28, 2024). https://www.eia.gov/todayinenergy/detail.php?id=62409.

6 Wamstead, Dennis, “Dominion Virginia’s Improbable IRP,” Institute for Energy Economics and Financial Analysis, (November 2023), https://ieefa.org/sites/default/files/2023-11/Dominion%20Virginias%20Improbable%20IRP_November%202023.pdf.

7 Miller, Rich, “Dominion: Virginia’s Data Center Cluster Could Double in Size,” Data Center Frontier, (October 11, 2023), https://www.datacenterfrontier.com/energy/article/33013010/dominion-virginias-data-center-cluster-could-double-in-size.

8 Swinhoe, Dan, “Dominion connected 15 data centers totaling 933MW in Virginia in 2023, 15 more expected in 2024.” Data Center Dynamics, (May 3, 2024), https://www.datacenterdynamics.com/en/news/dominion-connected-15-data-centers-totaling-933mw-in-virginia-in-2023-15-more-expected-in-2024/.

9 “Dominion Supplemental Projects.” Dominion Energy, PJM Transmission Expansion Advisory Committee (July 9, 2024), https://www.pjm.com/-/media/committees-groups/committees/teac/2024/20240709/20240709-item-08—dominion-supplemental-projects.ashx.

10 “FOIA request-Local variance for data centers located in the Counties of Fairfax, Loudoun, and Prince William (request #716-23-0961),” Virginia Department of Environmental Quality, FOIA request made by Piedmont Environmental Council. (Received February 12, 2023).

11 “Air quality, public health at risk from data center diesel generators,” Piedmont Environmental Council, (February 24, 2023), https://www.pecva.org/work/energy-work/take-action-the-air-we-breathe-is-at-risk/.

12 Loritz, Justin, “Power Systems Topic 130: Diesel Generator Maintenance (2023),” Kohler Energy Division, (July 24, 2024), https://resources.kohler.com/power/kohler/industrial/pdf/WF335951%2023IND%20No%20Load%20White%20Paper%20Update%20singpg.pdf

13 “Data Center Usage – Reclaimed and Potable_FOIA Request,” Loudoun Water, FOIA request made by Piedmont Environmental Council. (Received on March 11, 2024).

14 “Caroline County Water Withdrawal Open Comment,” Friends of the Rappahannock, (July 5, 2024), https://riverfriends.org/caroline-county-water-withdrawal-open-comment/.

15 “Global Data Center Trends 2024,” CBRE, (June 24, 2024), https://www.cbre.com/insights/reports/global-data-center-trends-2024.

16 Antonio, Olivio.,“Internet data centers are fueling drive for old power source: Coal,” Washington Post, (April 17, 2024), https://www.washingtonpost.com/business/interactive/2024/data-centers-internet-power-source-coal/.

17 “Study Resolution: Data Centers,” Joint Legislative Audit and Review Commission. (Authorized by the Commission on December 11, 2023). https://jlarc.virginia.gov/pdfs/resolutions/2024_Data%20centers_JLARC.pdf.

18 “Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board,” PJM Interconnection, (December 2023), https://pjm.com/-/media/committees-groups/committees/teac/2023/20231205/20231205-pjm-teac-board-whitepaper-december-2023.ashx.

19 “Reliability Analysis Report: 2022 RTEP Window 3,” PJM, (December 8, 2023), https://pjm.com/-/media/committees-groups/committees/teac/2023/20231205/20231205-2022-rtep-window-3-reliability-analysis-report.ashx.